Nanofabrication Facility
This project was one of UCC's PRTLI (Programme for Research in Third Level Insitutions) - Cycle I approved projects. The project was based at the NMRC in the Maltings. It involved the refurbishment of existing space within the NMRC to accommodate £7.36m of key research equipment (e-beam lithography system, cluster etching system, deep trench etcher, photolithography printing, microscopes, stone boxes, spectroscopy etc.). The refurbishment cost was £2.1m (€2.7m).
Project Team
Delivered by the UCC Capital Projects Team
Design Team
Project Management (Full Design Services)
Contractor
Leo Lynch (Main Mechanical Contractor)
Kirby (Electrical)
Update
This project was completed in April 2002.