Construction Update June 2008

27 May 2008
Construction Update June 2008

Tyndall New Laboratory Building

Construction Update June 2008 current activities:

  • RC main frame completed
  • Commencing 1st fix mechanical and electrical works first floor
  • Commenced installation of clean room on ground floor
  • Plant room and atrium steel delivered to site
  • Removal of Galbestos cladding Block B
  • Contined installation of underground services within Atrium ground floor
  • Close-out of the summer shutdown works
  • Completion of new CHW piping runs in Block A and loading platform for AHU replacement

Upcoming works: 

  • Erection of Block C roof plant rooms and complete permanent roof finishes
  • Commence M & E fit out to ground floor and 3rd floors and contine installation on 1st floor
  • Commence 2nd fix M & E to basement area
  • Progress internal room partitions on each floor
  • Continue external finishes to Block B & C
  • Continued works within the new Atrium area and structural upgrades at high level
  • Start erection of Atrium passenger lift and stairwell structural steel
  • Complete summer shutdown